Ostwal Builders Complaints & Reviews
Address: 401107 |
Website: Cheating from Ostwal Builders |
Post 8 month of the complaint above, we can not see any improvement from builders side. Infact situation is more worst. As I mentioned above Ostwal builder has a land acquisition issue at this site. Now he is using same access of building no 8 for bldg. No. 9, 10, 11 and 12. You can imagine a situation only one entrance for 320 flats which also using as exit. Not sure how corporation permits these projects. Now as he already given a possession...
Helpful
Found this helpful?
Address: 401107 |
I have purchased a flat at ostwal orchid bldg no. 8, i got very bad experience of customer support and delivery. The solar system he installed is not working at all. Now already more than 3 years happen after possession he is delaying the society formation as he is having some legal issues with the land title. He is now using the ostwal orchid 8 premises for construction of his new phase as the other land owner is not giving him access to...
Helpful
2 other people found this review helpful
2 found this helpful
Address: Thane, Maharashtra, 401107 |
Website: none |
Sir do something about construction quality in Mira road, there are lots of problems like seapages, leakages . the floor size is less then what was promised . faulty electrical materials .
How this builders are given clearances god only knows . they promised us in two months we get municipal water supply but still we rely on tankers . the builders to be elect society are seeking bribe of thousands of rs other wise they will cut the...
How this builders are given clearances god only knows . they promised us in two months we get municipal water supply but still we rely on tankers . the builders to be elect society are seeking bribe of thousands of rs other wise they will cut the...
Helpful
Found this helpful?
Address: Mumbai City, Maharashtra |
We had booked 2 apartments in Mira road project in September 2011.
We were told that possession will be completed by end of 2012.
After this project work was not even started until 2013. In addition to this delay at each stage we were given problems and were forced to keep making payments. At one time we were even forced to change our apartments floor for which we did not agree.
We were provide final possession letter in October 2014,...
Helpful
Found this helpful?
Ostwal Builders Recent Comments
- Cheater builder
Post 8 month of the complaint above, we can...1
- Complaint about the after sales service
I have purchased a flat at ostwal orchid bldg...4
- Significant delays and poor eperience with builder
We had booked 2 apartments in Mira road project...2