Hi all,
I have booked 1 BHK ultima in Venecia A, they say the cluster has completed its 9th slab.
I booked the flat on 30th jan 2011 (that was a sunday) and was asked to come on a weekday for site visit. On the next Tuesday I had a site visit, and here it is what i saw:
The cluster at the entrance is complete now (I guess its Magnecia C D E and F) with electricity and water connection. I was allowed to have a look at all the flats of a floor. the entire cluster is completely ready to be given away. But at the same time i observed that they didnt allowed me to look at the interior clusters and Magnecia completely blocks the view of other cluster at the interior of the township. But i must agree that the construction quality is good and the layouts of the flats are exactly what is reflected in their brouchers. the 8 floor structures are impressive but the 18 floors are only at 9-10 slab which will take a lot of time to get completed is what i guess.
As far as the customer service is concerned, yes there is a communication gap between the sales executive and customer care personel.
as of now no major problems has been experienced by me. I got the allotment letter within no time and registration is in progress, they say that it will happen by next week.
So far so good, I hope for the best and would really like to stay in touch with you guys for developments.
I would like to call all casa bella owners to join in casa bella city community at www.commonfloor.com where we all can discuss things and unit together against injustice.
Please join in
Hemant Kawalkar
hem.[protected]@gmail.com
I have booked 1 BHK ultima in Venecia A, they say the cluster has completed its 9th slab.
I booked the flat on 30th jan 2011 (that was a sunday) and was asked to come on a weekday for site visit. On the next Tuesday I had a site visit, and here it is what i saw:
The cluster at the entrance is complete now (I guess its Magnecia C D E and F) with electricity and water connection. I was allowed to have a look at all the flats of a floor. the entire cluster is completely ready to be given away. But at the same time i observed that they didnt allowed me to look at the interior clusters and Magnecia completely blocks the view of other cluster at the interior of the township. But i must agree that the construction quality is good and the layouts of the flats are exactly what is reflected in their brouchers. the 8 floor structures are impressive but the 18 floors are only at 9-10 slab which will take a lot of time to get completed is what i guess.
As far as the customer service is concerned, yes there is a communication gap between the sales executive and customer care personel.
as of now no major problems has been experienced by me. I got the allotment letter within no time and registration is in progress, they say that it will happen by next week.
So far so good, I hope for the best and would really like to stay in touch with you guys for developments.
I would like to call all casa bella owners to join in casa bella city community at www.commonfloor.com where we all can discuss things and unit together against injustice.
Please join in
Hemant Kawalkar
hem.[protected]@gmail.com
Hi all
Just to correct myself, the cluster i visited is Magnifica C. and there is no cluster named magnecia.
Hey sharad probably you will get the possession by next month end, you can have a site visit on week days.
But i have no clue whats going on at the interior of the township as they dont allow us to visit under construction clusters.
Hemant Kawalkar
Just to correct myself, the cluster i visited is Magnifica C. and there is no cluster named magnecia.
Hey sharad probably you will get the possession by next month end, you can have a site visit on week days.
But i have no clue whats going on at the interior of the township as they dont allow us to visit under construction clusters.
Hemant Kawalkar
HI Hemant,
Thanks for update.
Nice to hear I will get possession and hope you will get possesion soon.
I wana visit my flat but they didn't allow me.
Have you seen MAGNIFICA-C ? What about Road? What about innner facilities?
Please provide me your contact details.
So that we will be in touch.
Thanks a lot Once again.
Thanks,
Sharad Patil
[protected]
[protected]
Thanks for update.
Nice to hear I will get possession and hope you will get possesion soon.
I wana visit my flat but they didn't allow me.
Have you seen MAGNIFICA-C ? What about Road? What about innner facilities?
Please provide me your contact details.
So that we will be in touch.
Thanks a lot Once again.
Thanks,
Sharad Patil
[protected]
[protected]
Hi friends,
During the month of Nov / Dec 2010, I was continously reminded by Lodha Dwellers to submit the DD of Stamp Duty / Registration / MVAT as the Customer Care Staff was in a hurry to complete the registration of agreement formality. I made the DD from the bank and went to the Head Office during 1st week of January, 2011. The Customer Care Staff accepted the DD of Stamp Duty and MVAT from me and told me to keep the DD of Registration charges with me.(To be handed to the Asst Registrar during the date of registration) I was assured that I shall be called for completing the registration formalities within 15 days. However, even after repeated request, I was not given the date of registration.
One fine day in the last week of February 2011, I was informed that the work of construction of Serena cluster- Casa Bella has not yet commenced so Lodha Dwellers are not going on with the registration. I was further assured that the construction would start in March 2011 and I shall be given the date of registration soon.
However, the 3rd week of March shall end tomorrow and yet there is no call from Lodha Dwellers regd the date of registration.
Moreover, some investors have earlier already completed the registration formalities. Then why has Lodha Dwellers abruptly stopped the registration procedure ? Its really very disgusting very pathetic. There is a time frame for the DD's which I have submitted or it shall get lapsed causing inconvenience.
Lodha is such a great name. They are building the tallest tower in Mumbai. Lodha should be aware that their investors have invested their hard earned money in their project and they expect result. Lodha should stop playing with their emotions and start the construction of all towers of Casa Bella including Serena with immediate effect and should invite the investors for completing the registration formalities soon.
Hope good sense prevails upon Lodha !
Eijaz
During the month of Nov / Dec 2010, I was continously reminded by Lodha Dwellers to submit the DD of Stamp Duty / Registration / MVAT as the Customer Care Staff was in a hurry to complete the registration of agreement formality. I made the DD from the bank and went to the Head Office during 1st week of January, 2011. The Customer Care Staff accepted the DD of Stamp Duty and MVAT from me and told me to keep the DD of Registration charges with me.(To be handed to the Asst Registrar during the date of registration) I was assured that I shall be called for completing the registration formalities within 15 days. However, even after repeated request, I was not given the date of registration.
One fine day in the last week of February 2011, I was informed that the work of construction of Serena cluster- Casa Bella has not yet commenced so Lodha Dwellers are not going on with the registration. I was further assured that the construction would start in March 2011 and I shall be given the date of registration soon.
However, the 3rd week of March shall end tomorrow and yet there is no call from Lodha Dwellers regd the date of registration.
Moreover, some investors have earlier already completed the registration formalities. Then why has Lodha Dwellers abruptly stopped the registration procedure ? Its really very disgusting very pathetic. There is a time frame for the DD's which I have submitted or it shall get lapsed causing inconvenience.
Lodha is such a great name. They are building the tallest tower in Mumbai. Lodha should be aware that their investors have invested their hard earned money in their project and they expect result. Lodha should stop playing with their emotions and start the construction of all towers of Casa Bella including Serena with immediate effect and should invite the investors for completing the registration formalities soon.
Hope good sense prevails upon Lodha !
Eijaz
I booked an apt in Casabella 2 years back and facing similar harrasement from customer service. Lets can we unite and so something to file a complaints in consumer court against them?
Mail me at
pavan.rana.[protected]@gmail.com
Mail me at
pavan.rana.[protected]@gmail.com
Sharad its time for Party!!! hurrahhh
Anyone from Ecellencia ????
Agreed. I had sent across my payments on time. the customer care person handling my account (Khusboo singh) did not care to check the envelopes properly and missed out the check I had sent across.
She had the guts to tell me that I am responsible for not following it up with her and should pay the interest for the same
Some nerve indeed.
Also when I inquired about the open parking to closed parking issues for which we had made a paynment of 1 lakh she is telling me that it is charged by the builder for the property and not for parking..
I do think we should all go there and give them a sound thrashing
She had the guts to tell me that I am responsible for not following it up with her and should pay the interest for the same
Some nerve indeed.
Also when I inquired about the open parking to closed parking issues for which we had made a paynment of 1 lakh she is telling me that it is charged by the builder for the property and not for parking..
I do think we should all go there and give them a sound thrashing
Yes, customer care is very callous. Recently I had made my payment towards the plastering phase.
Khusboo singh the customer care person handling my account did not care to check the cheques I had sent . When I enquired after a month, she had the nerve to tell me that i should have followed up with her and I am responsible for paying the interest on the same
Also can someone inform me on the status of the open parking which we had purchased for 90000 from Lodha. Later on i realized that they were selling it illegally
What can be done
Khusboo singh the customer care person handling my account did not care to check the cheques I had sent . When I enquired after a month, she had the nerve to tell me that i should have followed up with her and I am responsible for paying the interest on the same
Also can someone inform me on the status of the open parking which we had purchased for 90000 from Lodha. Later on i realized that they were selling it illegally
What can be done
Anyone from excellencia cluster? Fed up with CC's reply of delay and delay and ...
Same is the case with us. We have a booked a house in Casa Rio by Lodha Group at Kalyan. They made a lot of follow up for the initial payment and even for the registration amount but now since a month has passed, we have not got the registration papers as of now. The customer care of Lodha is useless i should say, they never ever pick up the phone, it just rings, rings & rings. I dont know how much more problems we have to face further.
Sangeeta
Sangeeta
any one know status about excellencia CC?
Yes,
I totally agree with you ppl. I have booked flat in Casa bella gold and i am really surprised coz when ever i call to customer care there is no one to answer the call (sysstem used to say that).. Even those people are not replaying over mail as well.
I dont know what those ppl are doing in customer care. Either they are careless or they dont feel that they should talk to customer. I am talking about number[protected]. This is the number they have spread among all the customers.
If one doesnt believe they may try..
Regards,
Neel
I totally agree with you ppl. I have booked flat in Casa bella gold and i am really surprised coz when ever i call to customer care there is no one to answer the call (sysstem used to say that).. Even those people are not replaying over mail as well.
I dont know what those ppl are doing in customer care. Either they are careless or they dont feel that they should talk to customer. I am talking about number[protected]. This is the number they have spread among all the customers.
If one doesnt believe they may try..
Regards,
Neel
They are clearly backing out on promises. I beleive there are funds issues with this group. Can we urgently ask others also to join hands before this Lodha cheats us all. I have booked in Casa Bella Gold same fate ie paid the registration fees, but unable to get thru to any customer care agent. They are clearly in some problem. Also banks have stopped lending to them. We have to do something urgently. Chris M
They are in financial trouble. Even banks have stopped lending to them. All o[censored]s who have booked have been conned. We must unite to get our dues. Chris MD
I am planning to book a flat in casa rio. can anyone tell me what all things do I need to take care of?
will they give the possession of the flat by dec 2012 as promised.
Also would there be an issue of water logging during rainy season as the site is close to the river and a low lying area
will they give the possession of the flat by dec 2012 as promised.
Also would there be an issue of water logging during rainy season as the site is close to the river and a low lying area
Now the office visit at malalakshi for any issues also not useful. They made some online query form
Thanks for your feedback. I have booked flat in CASA BELLA MAGNIFICA CLUSTER.
My Customer Care Exec. told me I will get possession by the March End 2011.
Is this a right news?
Please let me know When we get together?
My Contact details : [protected]@yahoo.com, [protected]@gmail.com
[protected], [protected]
Thanks in advance.
Thanks,