[Resolved] Godrej Properties — Garden City Allotment DelayAhmedabad
S
satviky
from Gurgaon, Haryana
May 15, 2015
Address: Ahmedabad, Gujarat
I booked a flat in Godrej Garden City - Eden Q, in Ahmadabad, Its possession was promised in 2014. I have stopped hearing form them since mid 2014. I raised so many queries but I do not get response. I have raised queries via GP portal but later I find queries in closed status with comment that information has been provided to the customer. Inspite of repeated reminders, still I have no clue on when my flat would be handed over.
Was this information helpful?
No (0)
Yes (0)
Complaint marked as Resolved
Godrej Properties customer support has been notified about the posted complaint.
Verified Support
Jul 06, 2015
Godrej Properties Customer Care's response Dear Satviky,
Greetings from Godrej Properties Limited!
With regards to possession for Godrej Garden City -Eden Q, we would like to inform you that the flat inceptions are scheduled to tentatively begin from first week of August 2015.
Kindly get in touch with us for further queries at [protected]@godrejproperties.com along with your flat code and contact details.
Godrej Properties always believe in a relationship based on trust with our customers.
Regards
Godrej Properties Limited
I am Chandan Bipin Dattani and have booked a flat in Godrej garden city Ahmedabad and in their pinecrest project . First booking amount was paid on 6 / 6 / 2011 and allotment letter was issued to me dated 17 / 3 / 2012 . Agreement was made on 11 /2/2013
Which mentioned of giving possession on 28/2/2015 . Today we are talking on 11/10/2016 and there is no clue when are we going to get possession .
Several different schedules were given verbally on phone of July-15 to Oct-15 to Feb-16 to Aug-16 and as of today no confirmation . There is a threat in. I tract of 18% interest if payment is delayed .
We keep getting reminders from the time we get intimation but nobody talks about possession . All junior staff will come on line and will remain non. Committal as they have no clue . Senior management staff do not come on line . We. Looked flat on Godrej and [protected]@T name but got absolutely disappointed and such result is not expected from a reputed group like Godrej .
Do not they have to give 18 % for the period of delayed possession as we have made almost 90 % payment .
Customer satisfaction rating Customer satisfaction rating is a complex algorithm that helps our users determine how good
a company is at responding and resolving complaints by granting from 1 to 5 stars for each
complaint and then ultimately combining them all for an overall score. Read more
Which mentioned of giving possession on 28/2/2015 . Today we are talking on 11/10/2016 and there is no clue when are we going to get possession .
Several different schedules were given verbally on phone of July-15 to Oct-15 to Feb-16 to Aug-16 and as of today no confirmation . There is a threat in. I tract of 18% interest if payment is delayed .
We keep getting reminders from the time we get intimation but nobody talks about possession . All junior staff will come on line and will remain non. Committal as they have no clue . Senior management staff do not come on line . We. Looked flat on Godrej and [protected]@T name but got absolutely disappointed and such result is not expected from a reputed group like Godrej .
Do not they have to give 18 % for the period of delayed possession as we have made almost 90 % payment .