1) builder name - piyush tiwari ( director )
2) project name - group housing of the company named -shubhkamna lords of kindle developers private
- limited ( a shubhkamna - advert group company)
3) project location/address – plot no sc -01/d-1 sector -79, noida.
4) buyer name - vasiyat ali - s/o shri istyak ali.
5) present address - house no 126. Gali no – 9 wazirabad village delhi -110084. Phone – [protected]
- email id – [protected]@gmail.com
6) allotment of flat no. – t-3/a-601(T-3 is the tower no. A for the type of flat, 6 stands for block no and 1stand
- 1st floor. Area -1165 square fit.2-bed room +dd+kitchen+2toilets.
- agreement l.N.51.801/t-4/a-601/2013 dt 10.8.13 of kindle developers pvt ltd.
7) date of booking - amount paid rs 400000/- vide pnb cheque no –643460 dt 21.6.12 to kindle developers
- private limited.
8) total cost - rs 5183775/-
9) total amount paid - amount paid rs 400000/- vide pnb cheque no –643460 dt 21.6.12
- amount paid rs 400000/- vide pnb cheque no –008561 dt 13...07.12.
- amount paid rs 268790/- vide sbi cheque no –231315 dt 08...07.13.
- amount paid rs 1004720/- vide hdfc cheque no –057987 dt 15.10.13.
- amount paid rs 32063/- vide hdfc cheque no –061999 dt 08.10.14.
- amount paid rs 388783/- vide hdfc cheque no –107861 dt 05.02.15.
- total amount 48.117 % paid rs 2494319/- out of total cost rs 5183775/-
10) date of promised delivery – august -2016
11) delivery delayed - about 5% work done in 4 years against total amount 48.117 % paid.
12) comments :-
I. Builder`s intent from start – (A) when he pre-launched then booking amount was 4 lac, later later he said it is 8 lac. Intention was to extract more money.(B)at the time of launch he changed the payment plan and size, again intention was to extract more money.(C) about 5% work done in 4 years against total amount 48.117 % paid. Again builder pressurized to submit money against demand process by him.
Ii. 8, 00000 rs collected by builder up to july 2012 but agreement made after one year in 10.8.2013, this period not counted for delivery period resulting losses me.
Iii. My tower no changed by builder from – t-4/a-601 to – t-3/a-601 vide l.N51.801/t-4/a-601/2013 dt 26.11.13. Why?
Iv. In payment schedule water arrangement & electricity arrangement not included only % of payment collection is showing but percentage of construction and respectively time is not showing which is not justified. In my opinion builder`s intention is not build flats.
In this regard i want to justice from violation of laid down rules by builder.
(Vasiyat ali)
House no 126. Gali no – 9 wazirabad village delhi -110084
Was this information helpful?
Prateek wisteria sec 77 noida
Dear Sir,Prateek Wisteria maintenance team is not catering to complaints of residents.
This is urgent request.