Good day sir,
We need you help on below explained issue:
We applied a new motor connection under 2.5 acre land scheme (Load 3.77) on 01/12/2014 on the name of harbans kaur (Age 65 years), w/o ajit singh, village labangarh, teh samarala (Area under machhiwara sahib, sub station gulal).
As per tr on 18/07/16, as per estimate (6301091/16-17) amount of 107240 (Ba16n 477 / 6378) was deposited a year ago.
After deposit we made few requests material was not issued and after repeated requests, around after 5 months on 20/12/16 material was issued. Due to that delay wheat session was on and we was not bale to do ground work.
Due to delay in material issue we was not able to install poles as wheat season was on.
After wheat session we made again many repeated requests and again after 5 months ground work was completed.
Now all ground work is completed including wiring and from last one months we made around 15 requests to je and to sdo machhiwara sahib and till now connection is not operational as only jumper is remaining to connect.
Every time they say we will do it and nothing is happening and they are not telling us the cause of delay.
Would be grateful if you could help us as it is very difficult for my mother in 65 years of age to go to office and keep requesting.
We are burning diesel for rice fields even after paying inr 107240 form one year.
Also complete material was not issued. During pole & wiring we buy extra wires & other material from local market after paying extra money to complete installation work.
Hope, we will get help from your side.
Was this information helpful?
lite 4 waje di gai hoi hai VPO Bhogiwal
grid kup kalan thick ni krde n.a. phone chakde ne thick karwao
kehnde ne ghar gae sawere karange
Daso sade bache sonde ni
je tuc ni krde tai kis nu kahie