(On rs dag no 1268 & 1268/1778)

Fyki, 3 cases pending before the honourable civil judge, 1st court (Sr. Div.), barasat, north 24 pgs.

Ts 579 of 2016
Temporary injunction order :
(Order no 22 date :[protected]

The principle defendant is hereby restrained from creating any 3rd party interest
In the suit property without disclosing and/or mentioning about the pendency of
This litigation in the deed of transfer to be made by the principle defendant in favour
Of the proposed transferees of the suit property and or any portion thereof till the
Disposal of the suit. However it is made clear that the principle defendant may
Complete such construction and may also transfer the same and/or any part thereof
At their won risk but they will not be permitted to claim any equity for such construction subsequently.

Ts 1205 of 2015 :
Ad-interim injunction :
(Initially had ad-interim injunction ordered by hon. Dist. Court, barasat from 06.10.2015 but later
That ad-interim injunction was vacated by hon. 4th adj, barasat. On 18.05.2017)

Hon. Supreme court order dated :[protected]
(Diary no. 29395 of 2017)
http://supremecourtofindia.nic.in/case-status

We are not inclined to interfere with the impugned
Order passed by the high court.
The special leave petition is accordingly dismissed.
However, the trial court is directed to expedite the
Trial of suit no.1205 of 2015.

Ts 650 of 2015 :
Ad-interim injunction : pending
Was this information helpful?
No (0)
Yes (0)
Feb 26, 2018
Updated by Prudence
Kabya (case status)
Reckjoani, Rajarhat, Kol - 135
(on RS Dag no 1268 & 1268/1778)

fyki, 3 cases pending Before the Honourable Civil Judge, 1st Court (Sr. Div.), Barasat, North 24 Pgs.

TS 579 of 2016
Temporary Injunction order :
(Order No 22 Date :[protected]

The principle defendant is hereby restrained from creating any 3rd party interest
in the suit property without disclosing and/or mentioning about the pendency of
this litigation in the deed of transfer to be made by the principle defendant in favour
of the proposed transferees of the suit property and or any portion thereof till the
disposal of the suit. However it is made clear that the principle defendant may
complete such construction and may also transfer the same and/or any part thereof
at their won risk but they will not be permitted to claim any equity for such construction subsequently.

TS 1205 of 2015 :
Ad-Interim Injunction :
(initially had ad-interim injunction ordered by Hon. Dist. court, Barasat from 06.10.2015 but later
that ad-interim injunction was vacated by Hon. 4th ADJ, Barasat. on 18.05.2017)

Hon. Supreme Court Order Dated :[protected]
(Diary No. 29395 of 2017)
http://supremecourtofindia.nic.in/case-status

We are not inclined to interfere with the impugned
order passed by the High Court.
The special leave petition is accordingly dismissed.
However, the trial court is directed to expedite the
trial of Suit No.1205 of 2015.

Temporary Injunction : Pending (hearing stage)

TS 650 of 2015 :
Ad-Interim Injunction : Pending
 
3 Comments

Comments

Half baked news... In the Special Leave Petition preferred by the plaintiff, she has relied on and/or referred to the order passed by the honourable Civil Judge, 1st Court (Sr. Div) at Barasat, being no. 22 dated 21st April, 2017 in the matter of T.S 579 of 2016 in support of her claim. The honourable Supreme Court after duly taking the said order into consideration vis-à-vis the order dated 19th June, 2017 passed in C.O. No. 1899 of 2017 by honourable Justice Sanjib Banerjee of Kolkata High Court, has been pleased to uphold the later. Therefore no such requirement of disclosing the pendency of the litigation in the deed of transfer to be made by the principal defendant in favour of the proposed transferees of the same suit property and or any portion thereof till the disposal of the suit regarding which the honourable High Court of Kolkata and honourable Supreme Court of India have already held the observation as mentioned before.
Prudence's [Complaint's author] reply, Mar 10, 2018
no need to blindly believe anybody. better contact Barasat court and refer to TS 579/2016, TS 650/2015, TS 1205/2015 to know the truth.

probably customers will be able to differentiate between truth and lie.
atleast, he/she/they is/are admitting the instance of the litigations. if I am not mistaking grossly, earlier was misleading buyers saying work has been stop due to local syndicate problem or other excuses .

present order in place :
TS 579 of 2016

Temporary Injunction order :

(Order No 22 Date : 21-04-2017)

The principle defendant is hereby restrained from creating any 3rd party interest in the suit property without disclosing and/or mentioning about the pendency of this litigation in the deed of transfer to be made by the principle defendant in favour of the proposed transferees of the suit property and or any portion thereof till the disposal of the suit. However it is made clear that the principle defendant may complete such construction and may also transfer the same and/or any part thereof at their won risk but they will not be permitted to claim any equity for such construction subsequently.
We are being guided and protected by the Orders of the Ld. Barasat Court, The Hon'ble High Court at Calcutta and by the Hon'ble Supreme Court at India, we have already referred to such litigation and orders in our previous comments. Hence, if any one willing to believe in the baseless and frivolous statements made by the Unknown Users shall do it in their own risk and peril.
one consumer has filed a complaint before consumer forum demanding for possession or full refund (with penalty). hearing is scheduled on 5th Nov 2018.

Post your Comment

    I want to submit Complaint Positive Review Neutral Comment
    code
    By clicking Submit you agree to our Terms of Use
    Submit

    Contact Information

    Team Taurus / Kabya Case Status
    Matiaghata, West Bengal
    India
    File a Complaint