hi every one.
I am also flat bookie in Iris. In last 2 days i had visited Chembur office for their payment & site for 1st inspection.
the situation is worst.
1. possession was promised last year October. it has been delayed for ever.
2. Grill charges 11, 300 were not mentioned/discussed during agreement. Chembur office forced me for payment, threatening to delay the possession further.
3. extra charges for legalization.
4. during Inspection i had to make at least 20 remarks pending jobs inside flat. following are few major observations. these are all normal jobs which they expect us to tell them.
a) Overall cleaning /micro cleaning is pending.
b) Video phone has been fixed in place of television fixing area.
c) They say inverter shall not be fixed upstairs.
d) they will not provide hand showers(2no.s) for toilet tap.
e) all the locks, fittings are rusty & dirty.
f) they write in document "Godrej make" lock & provided local brand.
g) Grills are fixed on window are in such a way that elevation can not be used for any purpose(cloths drying, minor storage).
They promise so many things but never remember even one of those.
overall experience with EVEREST (vimal) builder is unsatisfactory.
Gopal
I am also flat bookie in Iris. In last 2 days i had visited Chembur office for their payment & site for 1st inspection.
the situation is worst.
1. possession was promised last year October. it has been delayed for ever.
2. Grill charges 11, 300 were not mentioned/discussed during agreement. Chembur office forced me for payment, threatening to delay the possession further.
3. extra charges for legalization.
4. during Inspection i had to make at least 20 remarks pending jobs inside flat. following are few major observations. these are all normal jobs which they expect us to tell them.
a) Overall cleaning /micro cleaning is pending.
b) Video phone has been fixed in place of television fixing area.
c) They say inverter shall not be fixed upstairs.
d) they will not provide hand showers(2no.s) for toilet tap.
e) all the locks, fittings are rusty & dirty.
f) they write in document "Godrej make" lock & provided local brand.
g) Grills are fixed on window are in such a way that elevation can not be used for any purpose(cloths drying, minor storage).
They promise so many things but never remember even one of those.
overall experience with EVEREST (vimal) builder is unsatisfactory.
Gopal
Even I am in agreement for the builders miscommunication of the unschedule & unindicated demand of VAT charges and that too blank cheque. I am seeking advice from colleagues to deal with subjective matter. In case anyone have any suggestion or advice then please let us know through the forum.
Hi,
Even i have booked a flat in Iris and the same miscommunication has been faced by me
i request all the iris customers to come together and strong action needs to be taken
Even i have booked a flat in Iris and the same miscommunication has been faced by me
i request all the iris customers to come together and strong action needs to be taken
Dear THANECITY...
My contact email id is gopalakrishna.[protected]@hotmail.com
do contact me for any need. i tried to fight alone with them, was loosing cause. i am ready to join hand with every one.
Dear Sushil,
i have issued cheque worth 5% of flat cost. not blank amount.
hope this info. may help you.
My contact email id is gopalakrishna.[protected]@hotmail.com
do contact me for any need. i tried to fight alone with them, was loosing cause. i am ready to join hand with every one.
Dear Sushil,
i have issued cheque worth 5% of flat cost. not blank amount.
hope this info. may help you.
Hi All,
Since currently I am in USA, I am not able to see the internal condition of the IRIS Flat myself. As i had mentioned in my previous comments, I am also going thorugh the same probs as you people.
But my Power of attorney holder, my relative, may not have noticed all the cleaning/fitting related issues.
The comments from Gopal are really helpfull to think in this directions.
And I see only comments from Gopal, and Sushil. There are 17 floors in the building, no one else has registered any complaints. This shows the lack of knowledge that our own people from India have.
We must do something that everyone should be made aware of these, so that it can be rectified.
Any ways, Like Gopal, I had also issues the 5% required VAT related cheque. I would be back to India only in Dec-2010. But do keep on posting these things. So that, everyone is aware of these.
These Builders only make call, at the time of money demands.
/Raman
Since currently I am in USA, I am not able to see the internal condition of the IRIS Flat myself. As i had mentioned in my previous comments, I am also going thorugh the same probs as you people.
But my Power of attorney holder, my relative, may not have noticed all the cleaning/fitting related issues.
The comments from Gopal are really helpfull to think in this directions.
And I see only comments from Gopal, and Sushil. There are 17 floors in the building, no one else has registered any complaints. This shows the lack of knowledge that our own people from India have.
We must do something that everyone should be made aware of these, so that it can be rectified.
Any ways, Like Gopal, I had also issues the 5% required VAT related cheque. I would be back to India only in Dec-2010. But do keep on posting these things. So that, everyone is aware of these.
These Builders only make call, at the time of money demands.
/Raman
Hey Guys,
Does anyone has a feedback on the IRIS Flat conditions, other than what Gopal has mentioned?
/Raman
Does anyone has a feedback on the IRIS Flat conditions, other than what Gopal has mentioned?
/Raman
Hey, I think very few people have knowledge of these forums, thats why, noone is registering their complaints in these forums.
Our own people are missing very basic educations, thats why these builders are making good use of the people, very easiliy fooling them. I dont see these kind of cheating, frauds etc here in USA.
.Raman
Our own people are missing very basic educations, thats why these builders are making good use of the people, very easiliy fooling them. I dont see these kind of cheating, frauds etc here in USA.
.Raman
HI All,
This is the problem with almost all IRIS bookers i guess.
The builder has got long list of things to claim from poor customers, but when its the time to deliver he has completely failed.
Its more than 6 months now that we are awaiting our possession but no sign of getting it.
Moreover, they have made several calls till the possession amount was givne to them and they also stated that after the clearance of the possession amount the customers can go and check the site and if there is anything pending the same could be rectified and then given to you within 15 days but unforftuantely they have not been able to rectify it, and its more that 20 days now and i see no sign of completion.
I am awaiting my flat keys and follwoing up continously with the chembur office and also their thane office guys who are our one point contact.
Is there anyone who has also completed his site visit the second time or hv got the keys, pls let us know.
This is the problem with almost all IRIS bookers i guess.
The builder has got long list of things to claim from poor customers, but when its the time to deliver he has completely failed.
Its more than 6 months now that we are awaiting our possession but no sign of getting it.
Moreover, they have made several calls till the possession amount was givne to them and they also stated that after the clearance of the possession amount the customers can go and check the site and if there is anything pending the same could be rectified and then given to you within 15 days but unforftuantely they have not been able to rectify it, and its more that 20 days now and i see no sign of completion.
I am awaiting my flat keys and follwoing up continously with the chembur office and also their thane office guys who are our one point contact.
Is there anyone who has also completed his site visit the second time or hv got the keys, pls let us know.
Hi,
I am also facing the same problem with the other Builder from pune. Now i thing these builder's are not sticking to there commitments and will fool the common man and attract more funds by deciving the customer by using the thrid grade materials. I think we can stop these activites of builder but we should have to take a strong action and these action should get published in the local as well as the national news paper. I am interested to make this happen but want some more mob to make this an event successful in pune an wish for all builder to take an immediate action so that end customer should be happy.
I am also facing the same problem with the other Builder from pune. Now i thing these builder's are not sticking to there commitments and will fool the common man and attract more funds by deciving the customer by using the thrid grade materials. I think we can stop these activites of builder but we should have to take a strong action and these action should get published in the local as well as the national news paper. I am interested to make this happen but want some more mob to make this an event successful in pune an wish for all builder to take an immediate action so that end customer should be happy.
Hi Gopal,
For miscommunication and any fault commitment from the builder u can take a guidance from the Consumer Forum which is useful.
For miscommunication and any fault commitment from the builder u can take a guidance from the Consumer Forum which is useful.
Hi,
Please stop discussing. You all are wasting your time in discussing. Take your possession and form a society and be united and then talk with builder.
Contact media so your voice can reach to massess, otherwise nothing going to happen.
Please stop discussing. You all are wasting your time in discussing. Take your possession and form a society and be united and then talk with builder.
Contact media so your voice can reach to massess, otherwise nothing going to happen.
Hello flat owners of Everest Countryside,
Pl.join community of everest countryside in commonfloor.com... this is a very good and unique way to be in touch, , ,
there are many issues with the builder now a days some of them are:
VAT
quality of construction
so we need to get united... pl. do join the community .. in case of any prob, pl. e-mail me at [protected]@yahoo.com so that I can send you the invitation... as on date, there are 10 flat owners who are able to be in touch through this site...
regards
Ramakant
IRIS building
Pl.join community of everest countryside in commonfloor.com... this is a very good and unique way to be in touch, , ,
there are many issues with the builder now a days some of them are:
VAT
quality of construction
so we need to get united... pl. do join the community .. in case of any prob, pl. e-mail me at [protected]@yahoo.com so that I can send you the invitation... as on date, there are 10 flat owners who are able to be in touch through this site...
regards
Ramakant
IRIS building
I really appreciate the initiative taken by ramakant. I am also facing the same bad muzic during flat possession from Everest IRIS project, I physically can not do, as I am right now in USA. My POA holder is only taking care of all the dealings.
I just keep on giving the money to this builder, and I have seen a lot of complaints since beginning.
I just keep on giving the money to this builder, and I have seen a lot of complaints since beginning.
Can u give details, how to join commonfloor, there are so many group for everest countryside.
ONLINE VAT REGN — PROBLEM IN WEB PAGE
fromjana samar <[protected]@gmail.com>[protected]@nic.in
dateThu, Sep 2, 2010 at 4:48 AM
subjectPROBLEM IN DATA ENTRY IN THE TIME OF SUBMISSION
mailed-bygmail.com
hide details 4:48 AM (0 minutes ago)
Dear Sir
I am very astonised for your NEW VAT REGISTRATION SYSTEM through on line.When I input the all data of all field of the web form and submit it then every time the CONTACT PERSON FIELD is back in blank form.For this problem I am not creat the field successfully.
So, please see the matter.
With thanks ,
Yuor,s faithfully,
Date: 02/09/2010. SAMAR JANA
Mobile No.[protected]
How to join Commonfloor.com
In following steps:
1. Select City: Mumbai
2. Apartment: Everest ... it will automatically give options.. select Everest countryside
Then join it...simple...
alternatively,
Pl. send me your e-mail ID, I will send you a proper invitation.
As on date there are around 15 residents. I expect more to join soon.. so lets stay together and lets be in touch...
Regards
Ramakant
[protected]@yahoo.com
In following steps:
1. Select City: Mumbai
2. Apartment: Everest ... it will automatically give options.. select Everest countryside
Then join it...simple...
alternatively,
Pl. send me your e-mail ID, I will send you a proper invitation.
As on date there are around 15 residents. I expect more to join soon.. so lets stay together and lets be in touch...
Regards
Ramakant
[protected]@yahoo.com
We are also another victims for this Everest Builders. We booked a flat in Iris on 1st dec, 2009 made the payments according to what the builders had demanded and we were following up from the very next day for registration and it was delayed from the builders end later we get a letter stating that booking will be terminated or you will be charged interest and when we followed up with the builder we spoke to Laxmi who informed us to just IGNORE the letter and this was told to us twice when we kept getting these letters. Finally when the payments were cleared they came up with interest on late payment and 5% VAT which was hidden from us at the time of booking. We should be liable for interest because the delay was from the builders end for registration and the VAT is still not applicable for those who have booked in the year 2009 till court comes up with their decision. Due their demand of never ending charges and the way the representative LAXMI treated our Father he had an HEART ATTACK and we had to again spend lakhs to get his life back which is precious to us than anything else in this world. So is this loss going to be covered by these builders and for this long time are they going to compensate to us. They should be charged for fraud, misleading information, mental torture. and stress...Dipti, Divya and Jerin.
Please share your email Ids. I have been a victim of similar treatment by Everest builders. My phone num is [protected] and email is [protected]@gmail.com.
We need to teach these guys a lesson. Their high handed behavious is getting out of hand.
We need to teach these guys a lesson. Their high handed behavious is getting out of hand.
Contact Information
Everest Builders
India
File a Complaint
I really appreciate first the people like you who are actually now using this forum. We shoud definitely do something for the society so that every one becomes at least aware of these kind of forums, and can put their complaints against these kind of issues.
Any ways, right now since I am in USA, I could not interact with the Builder directly. I could only make a phone call to them. One of the lady, called Laxmi and Pratit, there in chembur office, tome me that they would not encash the cheque til the 5% VAT case is clear. But I doubt, Once i had given the blank cheque. It is never going to come back to me.
But 1 thing I will always make sure that, I would need the VAT receipt, in case the blank cheque is encashed.
Otherwise, I will put the fraud case against the Everest builder.
Only 1 option was left with me, that was issue the cheque. I sent all the required cheques to my relateve, power of attorney holder. I would be back to India in Nov/Dec this yr end. The builder will be giving the possession after receiving the cheques.
Please let me know, what actions you have taken. We will definitely meet, once I would be back to India.
You can send me your contact number also at my personal id:: [protected]@yahoo.com
/Raman